Environmental
Management: Huntwood
Industries manufactures wood cabinets for residential and commercial
sale. SCAPCA
issued a Notice of Violation and Huntwood hired Spring Environmental to
conduct air dispersion modeling to determine if additional control
measure would be required. Spring
Environmental conducted air dispersion modeling of formaldehyde emission
and negotiated Notice of Construction permits for 6 paint booths.
A site environmental compliance inspection was conducted and an
action plan developed in coordination with site environmental manager.
An Integrated Emergency Plan (contingency/emergency
response/accident prevention/SPCC) was developed and a training program
designed to incorporate all facets of environmental and safety
requirements. Client: Huntwood Industries, Spokane, WA |